当前位置: 首页 > 软考高级职称 > 信息系统项目管理师 > ( )is the hierarchical breakdown of the entire scope of work by the project team to accomplish the project objectives and create the required deliverables, provides detailed deliverable,activity, and scheduling information about each component in the work breakdown structure.

1.【单选题】

( )is the hierarchical breakdown of the entire scope of work by the project team to accomplish the project objectives and create the required deliverables, provides detailed deliverable,activity, and scheduling information about each component in the work breakdown structure.

A

OLA

B

SLA

C

SOP

D

WBS