试题1
The uncertainty of an event is measured by its probability of occurrence and is inversely proportional to that. The more uncertain an event is. The more information is required to resolve uncertainty of that event. The amount of information is measured in ( )
A、possibility
B、bits
C、bps
D、probability
试题2
( )is a trem for data sets that are so large or complex that traditional data processing applications are inadequate. Challenges include analysis, capture . data curation. Search. Sharing. Storage . transfer. Visualization . querying updating and information privacy
A、Data market
B、Data varehouse
C、Big data
D、BI
试题3
某项目有40%的概率获利10万元,30%的概率会亏损8万元,30%的概率既不获利也不亏损。该项目的预期货币价值分析(EMV)是( )。
A、0元
B、1.6万元
C、2万元
D、6.4万元
答案解析:
试题1 参考答案:B
参考解析:
一个事件的不确定性的测量是通过其发生的概率是成反比的。是更加不确定事件。需要更多的信息来解决该事件的不确定性。以比特的信息量。
试题2 参考答案:C
参考解析:
大数据是一个非常大的或复杂的,传统的数据处理应用程序数据集是不够的。挑战包括分析,捕捉。数据管理。搜索。Sharing。存储。转移。可视化。查询更新与信息隐私。
试题3 参考答案:B
参考解析:
EMV=10*40%-8*30%+0*30%=1.6万元
备考福利:软考高级职称(高项)在线题库,内容包含章节习题、模拟试卷、历年真题等,点击下方图片即可开始在线刷题!
以上就是“信息系统项目管理师每日练习题及答案解析(472)”的内容了,请考生仔细阅读,提前进行备考。温馨提示:为帮助各位考生更好地备考软考高项考试,环球网校为大家特意上传了很多备考资料,如历年真题、模拟试题与答案解析、考试技巧等备考资料,考生可点击下方“免费下载”进行领取哦!
最新资讯
- 信息系统项目管理师每日练习题及答案解析(472)2026-01-22
- 信息系统项目管理师每日练习题及答案解析(471)2026-01-21
- 信息系统项目管理师每日练习题及答案解析(470)2026-01-20
- 信息系统项目管理师每日练习题及答案解析(469)2026-01-19
- 信息系统项目管理师每日练习题及答案解析(468)2026-01-18
- 信息系统项目管理师每日练习题及答案解析(467)2026-01-17
- 信息系统项目管理师每日练习题及答案解析(466)2026-01-16
- 信息系统项目管理师每日练习题及答案解析(465)2026-01-15
- 信息系统项目管理师每日练习题及答案解析(464)2026-01-14
- 软考题库在线刷题「信息系统项目管理师」每日一练(1月13日)2026-01-13